Dept. of Trans. PROGRESS Serial No. Contract No. 07-054-09-10 07-115454 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 19% 07-VEN-23-R3.5/R11.4 Federal Project: HP21-6207(36) LN-6207(36) Progress payment No. 11 Payment period ending: 02-20-07 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,049,991.43 3,221,360.72 2.a. Extra Work 263,694.67 0.00 b. Adjustment Comp. -52,975.00 0.00 3. Materials on Hand 502,612.42 -249,753.04 4. Earned Subject to Retention 18,763,323.52 2,971,607.68 5. Mobilization 1,377,500.00 0.00 6. Total Work Completed 19,638,211.10 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,140,823.52 2,971,607.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,971,607.68