Dept. of Trans. PROGRESS Serial No. Contract No. 01-296-15-19 07-115654 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 8% 07-LA-5743 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-01 ACE ENGINEERING INC 1880 WRIGHT AVE LA VERNE CA 917505824 Escrow No. 01838 Total Estimate This Estimate 1. Contract Itms Without Mobil. 61,562.60 61,562.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 61,562.60 61,562.60 5. Mobilization 6. Total Work Completed 61,562.60 7. Deductions 8. a.Contract Retentions -6,156.26 -6,156.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 55,406.34 55,406.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,406.34