Dept. of Trans. PROGRESS Serial No. Contract No. 02-206-13-13 07-115654 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 72% 07-LA-5743 Federal Project: NONE Progress payment No. 08 Payment period ending: 07-20-02 ACE ENGINEERING INC. 1880 WRIGHT AVE LA VERNE CA 917505824 Escrow No. 01838 Total Estimate This Estimate 1. Contract Itms Without Mobil. 405,898.90 19,476.31 2.a. Extra Work 114,654.50 42.72 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 520,553.40 19,519.03 5. Mobilization 6. Total Work Completed 520,553.40 7. Deductions 8. a.Contract Retentions -52,055.34 -1,951.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 468,498.06 17,567.13 10. Reduction Amt to Escrow 11. Payment to Escrow 52,050.00 12. Net Pymt. this Estimate 17,567.13