Dept. of Trans. PROGRESS Serial No. Contract No. 02-234-11-01 07-115654 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 79% 07-LA-5743 Federal Project: NONE Progress payment No. 09 Payment period ending: 08-20-02 ACE ENGINEERING INC. 1880 WRIGHT AVE LA VERNE CA 917505824 Escrow No. 01838 Total Estimate This Estimate 1. Contract Itms Without Mobil. 503,068.06 97,169.16 2.a. Extra Work 129,950.13 15,295.63 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 633,018.19 112,464.79 5. Mobilization 6. Total Work Completed 633,018.19 7. Deductions 8. a.Contract Retentions -63,301.82 -11,246.48 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 569,716.37 101,218.31 10. Reduction Amt to Escrow 11. Payment to Escrow 63,300.00 12. Net Pymt. this Estimate 101,218.31