Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-12-52 07-116794 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 20% 07-VEN-118-T18.2/R32.6 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-20-07 C A RASMUSSEN INC 2360 SHASTA WAY SIMI VALLEY CA 93065 Escrow No. 02301 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,921,068.61 2,517,194.86 2.a. Extra Work 24,399.51 17,976.10 b. Adjustment Comp. 3. Materials on Hand 1,219,990.67 513,719.51 4. Earned Subject to Retention 10,165,458.79 3,048,890.47 5. Mobilization 3,800,000.00 800,000.00 6. Total Work Completed 12,745,468.12 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -774,547.67 -62,890.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,190,911.12 3,795,999.63 10. Reduction Amt to Escrow 11. Payment to Escrow 774,540.00 12. Net Pymt. this Estimate 3,795,999.63