Dept. of Trans. PROGRESS Serial No. Contract No. 15-054-14-14 07-117074 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 07-LA-10-31.2/33.4 HP21-6207(48) CMLN-6207(48) Progress payment No. 072 Payment period ending: 02-20-15 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,081,367.50 -44,759.45 2. a. Extra Work 20,762,081.50 254,061.59 b. Adustment Comp. 778,852.17 480,621.41 3. Materials on Hand 4. Earned Subject to Retention 80,622,301.17 689,923.55 5. Mobilization 5,820,000.00 0.00 6. Total Work Completed 86,442,301.17 7. Deductions -75,271.32 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 86,367,029.85 689,923.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 689,923.55