Dept. of Trans. PROGRESS Serial No. Contract No. 14-237-14-52 07-1170U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 4% 07-LA-10-33.2/37.2 Federal Project: CMLN-6207(59) Progress payment No. 04 Payment period ending: 08-20-14 AMES CONSTRUCTION, INC. 391 N MAIN STREET SUITE 111 CORONA CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,975,313.24 1,346,638.30 2.a. Extra Work 17,925.14 10,703.95 b. Adjustment Comp. 3. Materials on Hand 711,405.50 177,911.50 4. Earned Subject to Retention 2,704,643.88 1,535,253.75 5. Mobilization 6. Total Work Completed 1,993,238.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,704,643.88 1,535,253.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,535,253.75