Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-12-13 07-1170U4 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 28% Location: Federal Project: 07-LA-10-33.2/37.2 CMLN-6207(59) Progress payment No. 022 Payment period ending: 11-20-15 AMES CONSTRUCTION, INC. 2000 AMES DRIVE BURNSVILLE, MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,122,295.34 1,212,909.51 2. a. Extra Work 755,634.29 11,926.52 b. Adustment Comp. 44,061.15 44,061.15 3. Materials on Hand 1,641,119.13 -89,571.00 4. Earned Subject to Retention 22,563,109.91 1,179,326.18 5. Mobilization 8,360,000.00 0.00 6. Total Work Completed 29,281,990.78 7. Deductions -7,800.00 -2,800.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,915,309.91 1,176,526.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,176,526.18