Dept. of Trans. PROGRESS Serial No. Contract No. 17-054-11-34 07-1170U4 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 50% Location: Federal Project: 07-LA-10-33.2/37.2 CMLN-6207(59) Progress payment No. 038 Payment period ending: 02-20-17 AMES CONSTRUCTION INC 2000 AMES DR BURNSVILLE MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,151,813.26 1,603,988.75 2. a. Extra Work 1,561,555.62 68,047.35 b. Adustment Comp. 44,061.15 0.00 3. Materials on Hand 1,356,899.83 -76,067.15 4. Earned Subject to Retention 43,114,329.86 1,595,968.95 5. Mobilization 8,360,000.00 0.00 6. Total Work Completed 50,117,430.03 7. Deductions -32,250.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,442,079.86 1,595,968.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,595,968.95