Dept. of Trans. PROGRESS Serial No. Contract No. 20-021-15-06 07-1170U4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 82% Location: Federal Project: 07-LA-10-33.2/37.2 CMLN-6207(59) Progress payment No. 073 Payment period ending: 01-20-20 AMES CONSTRUCTION INC 2000 AMES DR BURNSVILLE MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 76,000,696.86 1,224,718.64 2. a. Extra Work 4,269,118.49 -22,855.50 b. Adustment Comp. 17,801.26 0.00 3. Materials on Hand 3,677.02 -41,769.90 4. Earned Subject to Retention 80,291,293.63 1,160,093.24 5. Mobilization 8,800,000.00 0.00 6. Total Work Completed 89,087,616.61 7. Deductions -18,494.96 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 89,072,798.67 1,160,093.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,160,093.24