Dept. of Trans. FINAL Serial No. Contract No. 24-281-16-41 07-1170U4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-10-33.2/37.2 CMLN-6207(59) Progress payment No. 104 Payment period ending: 01-11-22 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 82,932,845.49 0.00 2. a. Extra Work 5,954,717.06 0.00 b. Adustment Comp. 38,367,767.69 36,000,000.00 3. Materials on Hand 4. Earned Subject to Retention 127,255,330.24 36,000,000.00 5. Mobilization 8,800,000.00 0.00 6. Total Work Completed 136,055,330.24 7. Deductions -18,494.96 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 136,036,835.28 36,000,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,000,000.00