Dept. of Trans. PROGRESS Serial No. Contract No. 01-360-13-54 07-117104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 43% 07-LA-14-44.0/R54.5 Federal Project: ACNH-P014(52) Progress payment No. 19 Payment period ending: 12-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01540 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,700,393.10 1,114,376.35 2.a. Extra Work 368,567.47 115,800.30 b. Adjustment Comp. 448,196.56 3,620.31 3. Materials on Hand 5,079.00 0.00 4. Earned Subject to Retention 16,522,236.13 1,233,796.96 5. Mobilization 2,471,000.00 0.00 6. Total Work Completed 18,988,157.13 7. Deductions -141,925.00 20,000.00 8. a.Contract Retentions -826,111.81 -61,689.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,025,199.32 1,192,107.11 10. Reduction Amt to Escrow 11. Payment to Escrow 826,110.00 12. Net Pymt. this Estimate 1,192,107.11