Dept. of Trans. PROGRESS Serial No. Contract No. 05-356-16-00 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 29% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 15 Payment period ending: 12-20-05 BALFOUR BEATTY CONSTRUCTION INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,172,037.60 1,603,107.80 2.a. Extra Work 756,174.69 25,041.10 b. Adjustment Comp. 3. Materials on Hand 189,109.82 0.00 4. Earned Subject to Retention 19,117,322.11 1,628,148.90 5. Mobilization 7,935,000.00 0.00 6. Total Work Completed 26,863,212.29 7. Deductions -108,200.00 -98,200.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,944,122.11 1,529,948.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,529,948.90