Dept. of Trans. PROGRESS Serial No. Contract No. 06-053-13-54 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 34% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 18 Payment period ending: 02-20-06 BALFOUR BEATTY CONSTRUCTION INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,261,897.88 1,331,542.84 2.a. Extra Work 987,639.26 90,057.51 b. Adjustment Comp. 3. Materials on Hand 422,389.82 136,080.00 4. Earned Subject to Retention 22,671,926.96 1,557,680.35 5. Mobilization 10,051,000.00 2,116,000.00 6. Total Work Completed 32,300,537.14 7. Deductions -108,200.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,614,726.96 3,673,680.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,673,680.35