Dept. of Trans. PROGRESS Serial No. Contract No. 07-330-10-54 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 41 Payment period ending: 11-20-07 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 70,089,224.39 2,695,577.85 2.a. Extra Work 5,743,749.05 88,761.98 b. Adjustment Comp. -104,731.43 -34,449.60 3. Materials on Hand 1,386,483.32 -67,240.00 4. Earned Subject to Retention 77,114,725.33 2,682,650.23 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 86,308,242.01 7. Deductions -491,630.45 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 87,203,094.88 2,682,650.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,682,650.23