Dept. of Trans. PROGRESS Serial No. Contract No. 07-360-15-01 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 89% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 42 Payment period ending: 12-20-07 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,353,827.46 2,264,603.07 2.a. Extra Work 5,775,716.25 31,967.20 b. Adjustment Comp. -110,990.23 -6,258.80 3. Materials on Hand 1,300,947.32 -85,536.00 4. Earned Subject to Retention 79,319,500.80 2,204,775.47 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 88,598,553.48 7. Deductions -158,400.00 333,230.45 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 89,741,100.80 2,538,005.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,538,005.92