Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-10-04 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 91% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 43 Payment period ending: 01-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 73,565,544.80 1,211,717.34 2.a. Extra Work 5,780,929.47 5,213.22 b. Adjustment Comp. -114,670.23 -3,680.00 3. Materials on Hand 1,270,094.43 -30,852.89 4. Earned Subject to Retention 80,501,898.47 1,182,397.67 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 89,811,804.04 7. Deductions -158,400.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -118,239.77 -118,239.77 c. Reduction after 95% Comp. 9. Total pay to Contractor 90,805,258.70 1,064,157.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,064,157.90