Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 08-032-14-52 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 91% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 44 Payment period ending: 01-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 73,567,389.80 1,845.00 2.a. Extra Work 5,809,818.28 28,888.81 b. Adjustment Comp. -114,670.23 0.00 3. Materials on Hand 1,270,094.43 0.00 4. Earned Subject to Retention 80,532,632.28 30,733.81 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 89,842,537.85 7. Deductions -158,400.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 118,239.77 c. Reduction after 95% Comp. 9. Total pay to Contractor 90,954,232.28 148,973.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 148,973.58