Dept. of Trans. PROGRESS Serial No. Contract No. 08-052-14-09 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 92% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 45 Payment period ending: 02-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,177,864.67 1,610,474.87 2.a. Extra Work 5,817,139.34 7,321.06 b. Adjustment Comp. -118,535.27 -3,865.04 3. Materials on Hand 1,158,240.10 -111,854.33 4. Earned Subject to Retention 82,034,708.84 1,502,076.56 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 91,456,468.74 7. Deductions -285,300.00 -126,900.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 92,329,408.84 1,375,176.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,375,176.56