Dept. of Trans. PROGRESS Serial No. Contract No. 08-086-09-03 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 94% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 46 Payment period ending: 03-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 76,297,596.04 1,119,731.37 2.a. Extra Work 5,840,949.06 23,809.72 b. Adjustment Comp. -118,535.27 0.00 3. Materials on Hand 1,322,290.53 164,050.43 4. Earned Subject to Retention 83,342,300.36 1,307,591.52 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 92,600,009.83 7. Deductions -315,636.00 -30,336.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 93,606,664.36 1,277,255.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,277,255.52