Dept. of Trans. PROGRESS Serial No. Contract No. 08-114-13-07 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 96% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 47 Payment period ending: 04-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,907,282.49 2,609,686.45 2.a. Extra Work 5,905,588.93 64,639.87 b. Adjustment Comp. -90,170.57 28,364.70 3. Materials on Hand 1,228,751.90 -93,538.63 4. Earned Subject to Retention 85,951,452.75 2,609,152.39 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 95,302,700.85 7. Deductions -315,636.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 96,215,816.75 2,609,152.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,609,152.39