Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-12-14 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 49 Payment period ending: 06-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 83,004,426.86 1,727,682.34 2.a. Extra Work 5,928,210.42 14,492.85 b. Adjustment Comp. -134,836.33 -44,665.76 3. Materials on Hand 1,027,844.33 -154,011.57 4. Earned Subject to Retention 89,825,645.28 1,543,497.86 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 99,377,800.95 7. Deductions -315,636.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 100,090,009.28 1,543,497.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,543,497.86