Dept. of Trans. PROGRESS Serial No. Contract No. 08-205-09-56 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 50 Payment period ending: 07-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 84,549,053.40 1,544,626.54 2.a. Extra Work 5,989,921.72 61,711.30 b. Adjustment Comp. -134,836.33 0.00 3. Materials on Hand 910,706.40 -117,137.93 4. Earned Subject to Retention 91,314,845.19 1,489,199.91 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 100,984,138.79 7. Deductions -317,753.90 -2,117.90 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 101,577,091.29 1,487,082.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,487,082.01