Dept. of Trans. PROGRESS Serial No. Contract No. 08-235-13-04 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 51 Payment period ending: 08-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,093,840.32 1,544,786.92 2.a. Extra Work 6,011,552.83 21,631.11 b. Adjustment Comp. -142,829.85 -7,993.52 3. Materials on Hand 882,277.35 -28,429.05 4. Earned Subject to Retention 92,844,840.65 1,529,995.46 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 102,542,563.30 7. Deductions -317,753.90 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 103,107,086.75 1,529,995.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,529,995.46