Dept. of Trans. PROGRESS Serial No. Contract No. 08-268-10-22 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 52 Payment period ending: 09-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 88,471,955.65 2,378,115.33 2.a. Extra Work 6,014,526.61 2,973.78 b. Adjustment Comp. -205,361.29 -62,531.44 3. Materials on Hand 845,562.35 -36,715.00 4. Earned Subject to Retention 95,126,683.32 2,281,842.67 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 104,861,120.97 7. Deductions -317,753.90 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 105,388,929.42 2,281,842.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,281,842.67