Dept. of Trans. PROGRESS Serial No. Contract No. 08-296-15-09 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 54 Payment period ending: 10-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 90,237,555.86 1,765,600.21 2.a. Extra Work 6,031,691.02 17,164.41 b. Adjustment Comp. -177,929.41 -37,711.92 3. Materials on Hand 822,963.04 -22,599.31 4. Earned Subject to Retention 96,914,280.51 1,722,453.39 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 106,671,317.47 7. Deductions -317,753.90 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 107,176,526.61 1,722,453.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,722,453.39