Dept. of Trans. PROGRESS Serial No. Contract No. 08-326-14-31 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 56 Payment period ending: 11-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 91,395,194.96 1,157,639.10 2.a. Extra Work 6,055,670.09 23,979.07 b. Adjustment Comp. -132,274.65 0.00 3. Materials on Hand 767,006.36 -55,956.68 4. Earned Subject to Retention 98,085,596.76 1,125,661.49 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 107,898,590.40 7. Deductions -607,162.90 -289,409.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 108,058,433.86 836,252.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 836,252.49