Dept. of Trans. PROGRESS Serial No. Contract No. 08-358-14-41 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 58 Payment period ending: 12-20-08 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 91,896,624.62 501,429.66 2.a. Extra Work 6,055,670.09 0.00 b. Adjustment Comp. -46,781.16 -12,038.40 3. Materials on Hand 765,506.36 -1,500.00 4. Earned Subject to Retention 98,671,019.91 487,891.26 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 108,485,513.55 7. Deductions -449,926.90 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 108,801,093.01 487,891.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 487,891.26