Dept. of Trans. PROGRESS Serial No. Contract No. 09-056-13-24 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 60 Payment period ending: 02-20-09 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 94,008,791.40 765,087.84 2.a. Extra Work 6,099,506.73 21,667.58 b. Adjustment Comp. 257,548.69 -14,024.88 3. Materials on Hand 351,002.00 -426,609.00 4. Earned Subject to Retention 100,716,848.82 346,121.54 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 110,945,846.82 7. Deductions -170,517.90 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 111,126,330.92 346,121.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 346,121.54