Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-14-25 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 62 Payment period ending: 04-20-09 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 98,047,045.53 1,396,485.60 2.a. Extra Work 6,174,317.42 10,004.25 b. Adjustment Comp. 243,865.97 -13,682.72 3. Materials on Hand 198,381.00 -7,040.00 4. Earned Subject to Retention 104,663,609.92 1,385,767.13 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 115,045,228.92 7. Deductions -170,517.90 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 115,073,092.02 1,385,767.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,385,767.13