Dept. of Trans. PROGRESS Serial No. Contract No. 09-203-11-59 07-1178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 07-LA-405-25.9/29.5 Federal Project: ACNH-405-3(48) I-405-3(48) STPC-6207(34) Progress payment No. 65 Payment period ending: 07-20-09 BALFOUR BEATTY INFRASTRUCTURE, INC 19435 WEST VALLEY HWY, S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,271,431.64 840,195.99 2.a. Extra Work 6,347,842.01 122,530.71 b. Adjustment Comp. 201,955.65 -41,910.32 3. Materials on Hand 43,080.00 -12,562.00 4. Earned Subject to Retention 106,864,309.30 908,254.38 5. Mobilization 10,580,000.00 0.00 6. Total Work Completed 117,401,229.30 7. Deductions -170,517.90 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 117,273,791.40 908,254.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 908,254.38