Dept. of Trans. 95% REDUCTION Serial No. Contract No. 10-145-13-13 07-1189A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 42% 07-VEN-150-9.6/9.6 Federal Project: NONE Progress payment No. 25 Payment period ending: 05-20-10 NCCI INC P O BOX 1422 PARAMOUNT CA 907231422 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,892,276.09 1,800.00 2.a. Extra Work 74,539.63 0.00 b. Adjustment Comp. -1,506.41 -1,506.41 3. Materials on Hand 4. Earned Subject to Retention 1,965,309.31 293.59 5. Mobilization 125,000.00 0.00 6. Total Work Completed 2,090,309.31 7. Deductions -16,224.48 0.00 8. a.Contract Retentions -98,265.47 -14.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 88,265.47 14.68 9. Total pay to Contractor 2,064,084.83 293.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 293.59