Dept. of Trans. PROGRESS Serial No. Contract No. 06-081-13-29 07-1190E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 77% 07-LA-1-7.1/30.7 Federal Project: ACST-P001(510) P-P001(510) Progress payment No. 07 Payment period ending: 03-20-06 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 706,960.00 214,750.00 2.a. Extra Work 8,183.52 2,956.30 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 715,143.52 217,706.30 5. Mobilization 209,000.00 0.00 6. Total Work Completed 924,143.52 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 924,143.52 217,706.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 217,706.30