Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-362-12-25 07-1190E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-1-7.1/30.7 Federal Project: ACST-P001(510) P-P001(510) Progress payment No. 16 Payment period ending: 12-07-06 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,980,520.15 75,680.20 2.a. Extra Work 157,091.54 35,077.51 b. Adjustment Comp. 4,147.73 -7,035.00 3. Materials on Hand 4. Earned Subject to Retention 2,141,759.42 103,722.71 5. Mobilization 220,000.00 0.00 6. Total Work Completed 2,361,759.42 7. Deductions -20,000.00 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,341,759.42 83,722.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 83,722.71