Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-057-14-35 07-1190E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-1-7.1/30.7 Federal Project: ACST-P001(510) P-P001(510) Progress payment No. 17 Payment period ending: 12-07-06 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,992,140.15 11,620.00 2.a. Extra Work 194,158.08 37,066.54 b. Adjustment Comp. 1,850.33 -2,297.40 3. Materials on Hand 4. Earned Subject to Retention 2,188,148.56 46,389.14 5. Mobilization 220,000.00 0.00 6. Total Work Completed 2,408,148.56 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,398,148.56 56,389.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,389.14