Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-212-09-20 07-1190F4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-1-9.9/ .0 Federal Project: ACST-S001(522) P-S001(522) Progress payment No. 09 Payment period ending: 05-31-07 K L M CONSTRUCTION INC 1011 E MAIN STE 408 PUYALLUP WA 98372 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 664,644.00 0.00 2.a. Extra Work 62,311.45 37,425.14 b. Adjustment Comp. -31,749.68 -50,765.63 3. Materials on Hand 4. Earned Subject to Retention 695,205.77 -13,340.49 5. Mobilization 90,000.00 0.00 6. Total Work Completed 785,205.77 7. Deductions 0.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 785,205.77 6,659.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,659.51