Dept. of Trans. PROGRESS Serial No. Contract No. 19-323-11-36 07-1193U4 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 52% Location: Federal Project: 07-LA-10-37.2/42.4 NHPI-010-1(829) CMLN-6207(70) Progress payment No. 047 Payment period ending: 11-20-19 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 111,536,554.22 3,997,323.40 2. a. Extra Work 8,782,009.39 -17,835.50 b. Adustment Comp. 5,968,425.58 0.00 3. Materials on Hand 2,101,497.50 -13,949.60 4. Earned Subject to Retention 128,388,486.69 3,965,538.30 5. Mobilization 16,162,297.00 0.00 6. Total Work Completed 142,449,286.19 7. Deductions -15,750.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 144,535,033.69 3,965,538.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,965,538.30