Dept. of Trans. PROGRESS Serial No. Contract No. 00-299-16-44 07-119464 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 40% 07-LA-105-9.6/10.0 Federal Project: NONE Progress payment No. 14 Payment period ending: 10-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01225 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,808,590.64 169,783.76 2.a. Extra Work 179,380.02 -410.52 b. Adjustment Comp. 3. Materials on Hand 211,947.89 91,709.45 4. Earned Subject to Retention 5,199,918.55 261,082.69 5. Mobilization 1,132,876.90 0.00 6. Total Work Completed 6,120,847.56 7. Deductions -24,415.88 -10,000.00 8. a.Contract Retentions -259,995.93 -13,054.14 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,048,383.64 238,028.55 10. Reduction Amt to Escrow 11. Payment to Escrow 259,990.00 12. Net Pymt. this Estimate 238,028.55