Dept. of Trans. SEMI-FINAL Serial No. Contract No. 03-268-14-10 07-119464 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-105-9.6/10.0 Federal Project: NONE Progress payment No. 51 Payment period ending: 06-30-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01225 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,900,818.76 0.00 2.a. Extra Work 759,777.96 73,602.73 b. Adjustment Comp. 1,161,101.24 -54,202.20 3. Materials on Hand 4. Earned Subject to Retention 12,821,697.96 19,400.53 5. Mobilization 1,192,502.00 0.00 6. Total Work Completed 14,014,199.96 7. Deductions -27,147.50 39,600.00 8. a.Contract Retentions -632,796.28 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 632,796.28 0.00 9. Total pay to Contractor 13,987,052.46 59,000.53 10. Reduction Amt to Escrow -632,790.00 0.00 11. Payment to Escrow 632,790.00 12. Net Pymt. this Estimate 59,000.53