Dept. of Trans. PROGRESS Serial No. Contract No. 03-113-10-06 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 5% 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 03 Payment period ending: 04-20-03 BALFOUR BEATTY CONSTRUCTION INC 1255 EAST HIGHLAND AVE STE 21 SAN BERNARDINO CA 92404 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 711,931.57 430,005.92 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 711,931.57 430,005.92 5. Mobilization 6. Total Work Completed 711,931.57 7. Deductions 8. a.Contract Retentions -71,193.16 -43,000.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 640,738.41 387,005.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 387,005.33