Dept. of Trans. PROGRESS Serial No. Contract No. 04-084-08-56 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 41% 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 15 Payment period ending: 03-20-04 BALFOUR BEATTY CONSTRUCTION INC ONE HARBOR CENTER SUITE 350 SUISUN CITY CA 94585 Escrow No. 02082 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,015,754.16 933,440.43 2.a. Extra Work 248,602.66 30,130.42 b. Adjustment Comp. 3. Materials on Hand 264,676.16 0.00 4. Earned Subject to Retention 9,529,032.98 963,570.85 5. Mobilization 2,565,000.00 0.00 6. Total Work Completed 11,829,356.82 7. Deductions -30,000.00 0.00 8. a.Contract Retentions -498,384.92 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,565,648.06 963,570.85 10. Reduction Amt to Escrow 11. Payment to Escrow 498,380.00 12. Net Pymt. this Estimate 963,570.85