Dept. of Trans. PROGRESS Serial No. Contract No. 04-174-09-39 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 51% 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 18 Payment period ending: 06-20-04 BALFOUR BEATTY CONSTRUCTION INC ONE HARBOR CENTER SUITE 350 SUISUN CITY CA 94585 Escrow No. 02082 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,042,686.32 782,047.13 2.a. Extra Work 376,432.05 43,446.73 b. Adjustment Comp. 3. Materials on Hand 639,864.53 376,273.65 4. Earned Subject to Retention 13,058,982.90 1,201,767.51 5. Mobilization 2,565,000.00 0.00 6. Total Work Completed 14,984,118.37 7. Deductions -30,000.00 -10,000.00 8. a.Contract Retentions -652,949.15 -60,088.38 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,941,033.75 1,131,679.13 10. Reduction Amt to Escrow 11. Payment to Escrow 652,940.00 12. Net Pymt. this Estimate 1,131,679.13