Dept. of Trans. PROGRESS Serial No. Contract No. 04-329-15-24 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 66% 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 23 Payment period ending: 11-20-04 BALFOUR BEATTY CONSTRUCTION INC ONE HARBOR CENTER SUITE 350 SUISUN CITY CA 94585 Escrow No. 02082 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,343,422.10 794,039.79 2.a. Extra Work 556,836.63 17,846.88 b. Adjustment Comp. 3. Materials on Hand 760,328.38 53,883.18 4. Earned Subject to Retention 16,660,587.11 865,769.85 5. Mobilization 2,700,000.00 0.00 6. Total Work Completed 18,600,258.73 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -833,029.36 -43,288.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,517,557.75 832,481.35 10. Reduction Amt to Escrow 11. Payment to Escrow 833,020.00 12. Net Pymt. this Estimate 832,481.35