Dept. of Trans. PROGRESS Serial No. Contract No. 05-115-07-13 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 79% 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 28 Payment period ending: 04-20-05 BALFOUR BEATTY CONSTRUCTION INC ONE HARBOR CENTER SUITE 350 SUISUN CITY CA 94585 Escrow No. 02082 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,951,807.12 337,846.47 2.a. Extra Work 707,747.13 43,643.13 b. Adjustment Comp. 33,050.41 0.00 3. Materials on Hand 732,535.99 -126,759.50 4. Earned Subject to Retention 19,425,140.65 254,730.10 5. Mobilization 2,700,000.00 0.00 6. Total Work Completed 21,392,604.66 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -971,257.03 -12,736.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,133,883.62 231,993.60 10. Reduction Amt to Escrow 11. Payment to Escrow 971,250.00 12. Net Pymt. this Estimate 231,993.60