Dept. of Trans. PROGRESS Serial No. Contract No. 07-082-08-01 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 54 Payment period ending: 03-20-07 BALFOUR BEATTY INFRASTRUCTURE INC 19435 WEST VALLEY HWY S-100 KENT, WA 98032 Escrow No. 02082 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,076,107.41 90,468.00 2.a. Extra Work 2,751,230.06 618,979.94 b. Adjustment Comp. 1,472,062.19 0.00 3. Materials on Hand 4. Earned Subject to Retention 29,299,399.66 709,447.94 5. Mobilization 2,700,000.00 0.00 6. Total Work Completed 31,999,399.66 7. Deductions -50,000.00 0.00 8. a.Contract Retentions -1,464,969.98 -35,472.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,484,429.68 673,975.55 10. Reduction Amt to Escrow 11. Payment to Escrow 1,464,960.00 12. Net Pymt. this Estimate 673,975.55