Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-11-15 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 55 Payment period ending: 04-20-07 BALFOUR BEATTY INFRASTRUCTURE INC 19435 WEST VALLEY HWY S-100 KENT, WA 98032 Escrow No. 02082 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,127,801.21 51,693.80 2.a. Extra Work 3,309,044.60 557,814.54 b. Adjustment Comp. 1,460,056.00 -12,006.19 3. Materials on Hand 4. Earned Subject to Retention 29,896,901.81 597,502.15 5. Mobilization 2,700,000.00 0.00 6. Total Work Completed 32,596,901.81 7. Deductions -50,000.00 0.00 8. a.Contract Retentions -1,494,845.09 -29,875.11 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 31,052,056.72 567,627.04 10. Reduction Amt to Escrow 11. Payment to Escrow 1,494,840.00 12. Net Pymt. this Estimate 567,627.04