Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-107-10-21 07-1198U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-405-21.3/26.4 Federal Project: ACNH-405-3(32) I-405-3(32) Progress payment No. 67 Payment period ending: 04-01-08 BALFOUR BEATTY INFRASTRUCTURE INC 19435 WEST VALLEY HWY S-100 KENT, WA 98032 Escrow No. 02082 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,269,946.79 20,262.40 2.a. Extra Work 6,909,500.41 183,035.12 b. Adjustment Comp. 1,481,989.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 33,661,436.69 203,297.52 5. Mobilization 2,700,000.00 0.00 6. Total Work Completed 36,361,436.69 7. Deductions -72,500.00 -22,500.00 8. a.Contract Retentions -1,672,906.96 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,672,906.96 1,672,906.96 9. Total pay to Contractor 36,288,936.69 1,853,704.48 10. Reduction Amt to Escrow -1,672,900.00 -1,672,900.00 11. Payment to Escrow 1,672,900.00 12. Net Pymt. this Estimate 180,804.48