Dept. of Trans. PROGRESS Serial No. Contract No. 06-331-08-49 07-1199U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 100% 07-LA-101-0.4/0.9 Federal Project: NONE Progress payment No. 29 Payment period ending: 11-20-06 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02188 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,874,700.59 264,722.20 2.a. Extra Work 314,075.91 0.00 b. Adjustment Comp. 4,938.05 -64,000.00 3. Materials on Hand 8,043.51 -7,556.59 4. Earned Subject to Retention 10,201,758.06 193,165.61 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 11,493,714.55 7. Deductions -127,300.00 -89,300.00 8. a.Contract Retentions -510,087.90 -9,658.28 b. Unsatisfactory Prog. -156,369.78 -9,658.28 c. Reduction after 95% Comp. 9. Total pay to Contractor 10,708,000.38 84,549.05 10. Reduction Amt to Escrow 11. Payment to Escrow 510,080.00 12. Net Pymt. this Estimate 84,549.05