Dept. of Trans. PROGRESS Serial No. Contract No. 07-082-08-01 07-1199U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 100% 07-LA-101-0.4/0.9 Federal Project: NONE Progress payment No. 33 Payment period ending: 03-20-07 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02188 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,451,658.43 351,210.00 2.a. Extra Work 447,894.19 62,444.69 b. Adjustment Comp. -121,267.64 -135,035.40 3. Materials on Hand 8,043.51 0.00 4. Earned Subject to Retention 11,786,328.49 278,619.29 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 13,078,284.98 7. Deductions -674,973.25 -135,273.25 8. a.Contract Retentions -589,316.42 -13,930.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,822,038.82 129,415.08 10. Reduction Amt to Escrow 11. Payment to Escrow 589,310.00 12. Net Pymt. this Estimate 129,415.08