Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-10-23 07-1199U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 100% 07-LA-101-0.4/0.9 Federal Project: NONE Progress payment No. 34 Payment period ending: 04-20-07 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02188 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,658,299.23 206,640.80 2.a. Extra Work 520,039.00 72,144.81 b. Adjustment Comp. -121,267.64 0.00 3. Materials on Hand 2,527.59 -5,515.92 4. Earned Subject to Retention 12,059,598.18 273,269.69 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 13,357,070.59 7. Deductions -713,973.25 -39,000.00 8. a.Contract Retentions -602,979.91 -13,663.49 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,042,645.02 220,606.20 10. Reduction Amt to Escrow 11. Payment to Escrow 602,970.00 12. Net Pymt. this Estimate 220,606.20